Status ExpNbr Date Authordown Type Category Target-Source Subject Text Attachments
Fixede748 Thu Jun 1 09:29:50 2017 Adrien MattaMUST2Hardware Telescope cabling debbug in G3Test performed without vaccum, in the dark,
cooling at 20.
  
Fixede748 Thu Jun 1 09:32:38 2017 Adrien MattaMUST2Hardware MUST2 cabling schemeThe MUST2 cabling scheme has been change so
Telescope 1 to 4 and 5 to 8 are on two independent
set of distribution box and HV Card.
  
Fixede748 Tue Jun 6 09:07:34 2017 Adrien MattaBEAMGeneral Moving to D6M2C Chamber now in D6 after a smooth ride,
ready to be aligned.
  
Fixede748 Sat Jun 17 10:22:43 2017 Adrien MattaEXLHardware EXL ADC gateEXL ADC is now setup with individual gate
on the ADC. 
  
Fixede748 Sat Jun 17 10:27:26 2017 Adrien MattaONLINESoftware Starting the GRU online analysisWe setup a script to start the right environment
to run GRU, ganil2root and nptool.
  
Fixede748 Sat Jun 17 10:32:25 2017 Adrien MattaONLINESoftware Online/Offline list of taskWe need to do the following improvement to
the online / offline environment:
  
Fixede748 Sat Jun 17 10:56:09 2017 Adrien MattaBEAMGeneral JC Thomas plans for the beam productionHere are a few notes by Jean Charles about
the expected LISE setting based on 2013 and
2014 16C tuning.
 REX-E628.pdf 
Fixede748 Sun Jun 25 09:53:44 2017 Adrien MattaRUNGeneral3-alphaRun 18Junk   
Fixede748 Sun Jun 25 09:54:08 2017 Adrien MattaRUNGeneral3-alphaRun 19 Source: 3-alpha + 60Co
Trigger: T1-8 or EXL
  
Fixede748 Mon Jun 26 09:15:31 2017 Adrien MattaRUNGeneral3-alphaRun 19 : disk quota exceededRun 19 was still running this morning, but
file stop writting at 6 O'Clock, when the
disk quota exceeded (we wrtoe about 14Go
  
Fixede748 Sat Jul 1 09:27:46 2017 Adrien MattaOTHERGeneralN/ASHIFT TABLE    
Fixede748 Sat Jul 1 10:47:18 2017 Adrien MattaBEAMGeneralN/APrimary beam energy measurementPCP delivered the primary beam energy measurement  IMG_1984.JPG 
Fixede748 Thu Jul 6 13:37:37 2017 Adrien MattaOFFLINEGeneralN/AEnergy loss table for d, 3He and 3HHere it is!  20x 
Pinnede744 Thu Mar 15 10:50:00 2018 Adrien MattaMUST2Hardware  Distribution box LPCCabling file by Fabien Naury (LPC).  8x 
Fixede744 Tue Apr 17 09:07:55 2018 Adrien MattaDAQGeneralN/ADAQ issue summaryPreviously on e744:

After a chat with Charles Houarner we decided
  
Fixede744 Fri May 25 08:37:04 2018 Adrien MattaMUST2HardwareN/AMUST2 coolingVacuum at 1.7 e-5 torr this morning.
I started the MUST2 cooling, setting both
coolers at -5C.
  
Fixede748 Wed Jun 7 11:29:55 2017 AdrienMECHHardwareN/ASurveyor mesurementThe surveyor are carrying out the measurement
of the detectors in D6.
The measurement should take the day, starting
  
Fixede748 Fri Jun 9 12:30:49 2017 AdrienVACUUMHardware Vacuum LeaksWe reach a stable 1e-5 mbar. We performed
a leak check and identify that the Ionisation
chamber gate valve is not totally tight,
  
Fixede748 Fri Jun 9 12:33:25 2017 AdrienMECHGeneral MUST2 positionAfter a the surveyor came we figured out the
MUST2 telescope are 1cm too high with respect
to the beam line.
  
Fixede748 Fri Jun 9 12:34:18 2017 AdrienDAQHardware HubWe are currentlky waiting for the hub to be
configured so we can start the MUST2 DAQ.
Should be done in the afternoon.
  