Fixed | e744 |
Fri May 18 17:38:21 2018 |
Francois and Pedja | OTHER | Hardware | | translator nim to ecl | There was a problem with the scalers, not
all of them were working. After several tests,
we changed the electronic module, from Lecroy |
|
Pending | e744 |
Wed May 30 15:26:40 2018 |
Francois Marlete | BEAM | General | | problem with beam | 14H00 : The primary beam was misaligned, they
are still working on it. No 14O beam. |
|
Ongoing | e744 |
Wed May 16 09:49:26 2018 |
Francois & Ruxandra & Armel | BEAM | Hardware | | E1D6 and E2D6 detectors | After struggling with the noise, we achieved
~ 50 keV resolution.
|
|
Fixed | e744 |
Mon May 28 12:22:42 2018 |
Francois & Marlete | OFFLINE | General | | superposition exp / theory for 15O and 15F | |
 |
Fixed | e744 |
Sun Apr 29 20:37:58 2018 |
Francois | CATS | General | | Chronogram | |
|
Ongoing | e744 |
Mon May 14 12:57:44 2018 |
Francois | TARGET | General | | target preparation |
Cibles Georges
|
|
Pending | e744 |
Tue May 22 19:40:26 2018 |
Francois | BEAM | General | | Planning of the experiment | |
|
Pending | e744 |
Sat May 26 13:22:08 2018 |
Francois | BEAM | General | | problem with CSS1 | There is a leakage of water in cavity north
of cyclotron CSS1. I discussed with Alain
Savale.
|
|
Fixed | e744 |
Tue May 29 10:42:00 2018 |
Francois | BEAM | General | | effective beam time | In total, there were:
1.4 UT of 14O, average 2x10^5 pps
|
|
Fixed | e755 |
Sun Jun 24 09:48:46 2018 |
Francois | BEAM | General | | No beam | 9H10: D5 stopped at 9H10. We asked for the
beam.
|
|
Fixed | e744 |
Tue May 29 02:01:58 2018 |
Franck, Valerian, Phil | RUN | General | Carbon | Run 2104 - Target 1 Carbon | Run 2104
Beam: 14O
Start @ 2:00 29 May 2018
|
 |
Fixed | e744 |
Tue May 29 02:38:21 2018 |
Franck, Valerian, Phil | ONLINE | General | Carbon | Spectra and HV Start Run 2104 | |
11x |
Fixed | e744 |
Tue May 29 04:08:52 2018 |
Franck, Valerian, Phil | RUN | General | Carbon | Run 2105 - Target 1 Carbon | Run 2105
Beam 14O
|
 |
Ongoing | e744 |
Tue May 29 06:09:58 2018 |
Franck, Phil | RUN | General | Carbon | Run 2106 - Target 1 Carbon | Run 2106
Beam 14O (CATS: 1.4e5 pps)
|
 |
Ongoing | e744 |
Tue May 29 07:39:53 2018 |
Franck, Phil | RUN | General | Carbon | Run 2107 - Restart after Reboot of VXI - Same problem | Low FAG rate: 30 /s
Low ORD rates: 0-10 /s, 15 /s on MM5 |
|
Fixed | e738 |
Wed Jul 11 09:32:37 2018 |
Franck, Jacques, Daisuke | RUN | General | Cryo-LH2 | Run 342 | Wed 11 July 2018
Start @ 9:19
|
10x |
Ongoing | e738 |
Wed Jul 11 15:41:33 2018 |
Franck, Jacques, Daisuke | RUN | General | Cryo-LH2 | Run 347 | Run 347 Start 15:28 stop 17h17
e748 Exxx 3,6G 11 juil. 17:17 /data/e748X/e755/acquisition/run/run_0347.dat.11-07-18_15h28m32s
CATS thresholds lowered from 40 to 24 mV
|
   |
Fixed | e738 |
Wed Jul 11 12:04:29 2018 |
Franck, Jacques + CATS Team | CATS | General | N/A | Run 343 - CATS2 pulser calibration | Start 11:53
Stop 11:59
|
|
Fixed | e748 |
Mon Jul 3 14:28:09 2017 |
Franck et Valérian | CHIO | Hardware | N/A | CHIO's electronic scheme | A quick scheme of the CHIO electronic. The
patch outputs are the one from the LISE acquisition
room. |
|
Fixed | e748 |
Tue Jul 4 20:27:59 2017 |
Franck et Valérian | CHIO | Hardware | N/A | UPDATE : CHIO's electronic scheme (valid from run 217) | Modification of the scheme to add the delay