Statusdown ExpNbr Date Author Type Category Target-Source Subject Text Attachments
Fixede744 Fri May 25 21:37:45 2018 iulian nicolas valérieRUNGeneralN/Arun 1012 all triggers 14O beam in D4   Run1012_E1_TcatsHF.pngRun1012_E1_T1HF_D6.png 
Fixede744 Fri May 25 22:03:12 2018 e744 Must2+LISE teamsRUNGeneralCH2RUNS 2000, 2001Beam 14O
Run 2000 start with all triggers, including
LISE trigger, during 1 minute for tests.
 6x 
Fixede744 Fri May 25 22:46:26 2018 e744 Must2+LISE teams, edit ValérieRUNGeneralCH2RUN 2004
 Run 2004   Date : 25/05/2018 22:45:58  25/05/2018
23:17:39 
 6x 
Fixede744 Fri May 25 23:26:23 2018 e744 Must2+LISE teams, edit ValérieRUNGeneralCH2START NARVAL, new versionthe NARVAL version is now reinstalled by Fred
Saillant.
see plot  ResolProblemNarvalEndofRun25may23h.png
 ResolProblemNarvalEndofRun25may23h.png 
Fixede744 Fri May 25 23:33:27 2018 iulianOTHERHardwareCH2changes after run 2004Target was changed to target number 5 (CH2
100 um GOODFELLOW)
The T_EXL1718 ok
 impact_matrix_run_2005.png 
Fixede744 Sat May 26 00:24:50 2018 e744 valérieDAQGeneralCH2change of trigger and divisionTRIGGER entry for CATS, presently IN8, seems
to be not running. We put it on IN7(Gatconf
=64).
 TRIGGERgmtChangedForCATS.png 
Fixede744 Sat May 26 00:38:38 2018 e744 all night shift teams, (edit) ValérieRUNGeneralCH2Run 2010RUN 2010
Date : 26/05/2018 00:37:44
 Target n°5  CH2 100 µm 
 20x 
Fixede744 Sat May 26 01:41:19 2018 e744 night shift team, edit valérieDAQGeneralCH2summary GMT, DAS config since run2005 Triggers: all except LISE

IN1 to IN5 : MM1 to MM5;
 chronoGMTmasterRun14O.pngchronogramGMTslave_Run14O.pngConfigDASThresMUST2at1MeV.pngConfigTDCTestParamInpectch0.png 
Fixede744 Sat May 26 02:39:18 2018 Mihai, PedjaRUNGeneralCH2Run 2011, Target n°5RUN 2011
Date : 26/05/2018 
Beam used: 14O
 9x 
Fixede744 Sat May 26 04:24:16 2018 Mihai, PedjaRUNGeneralCH2Run 2012, Target n°5RUN 2012
Date : 26/05/2018 
Beam used: 14O
 Scalers_start_run2012.png 
Fixede744 Sat May 26 05:16:12 2018 Iulian Valerian, pedja, mihaiTARGETGeneralCH2Target changeTarget No 4 is placed in-beam 5h15.   
Fixede744 Sat May 26 05:23:12 2018 Mihai, PedjaRUNGeneralCH2Run 2013, Target n°4RUN 2013
Date : 26/05/2018 
Beam used: 14O
 Scalers_start_run2013.pngRun2014MM_IMPACT5h53.png 
Fixede744 Sat May 26 05:51:00 2018 Mihai, PedjaRUNGeneralCH2Run 2014, Target n°4[U][B]RUN 2014[/B][/U]
Date : 26/05/2018 
Beam used: 14O
 9x 
Fixede744 Sat May 26 06:05:13 2018 Iulian Valerian PedjiaTARGETGeneralCH2Target issue No5In the attached figure it could be seen that
with the target No5 (run 2010) lower energy
resonances were visible (lower part of the
 Target_Issue_2004_2010_corrected_withGeorgesTarget.png 
Fixede744 Sat May 26 09:33:48 2018 Giuseppe, DieterRUNGeneralCH2run 2015Missing strips:
x
MM1 1
 MUST2_end_run2016.pngScalers_stop_run2015.pngMUST2_y_ongoing_run2018.png 
Fixede744 Sat May 26 10:03:37 2018 Giuseppe, DieterRUNGeneral run 2016& 2017

Problems with the ACQ (merger), they were
  
Fixede744 Sat May 26 11:19:37 2018 Giuseppe, DieterRUNGeneralCH2interruption due to to waterleak ibn CSS110:50 h Water leak at CSS1
        cryo pumps have to be regenerated
        continuation until the expert intervention
  
Fixede744 Sat May 26 11:42:03 2018 Giuseppe, DieterRUNGeneralCH2run 2019Run 2019

 scalers_start_run2019.pngscalers_stop_run2019.png 
Fixede744 Sat May 26 14:03:27 2018 Giuseppe, Dieter, J. EricRUNGeneralCH2Run 2020run 2020

 9x 
Fixede744 Sat May 26 16:31:53 2018 Jaromir, GiuseppeEXL-PPTSoftwareN/AEXL calibration, light leakSelector.C can be used to adjust energy bad
reconstruction in the EXL detectors due to
energy leak (see the PDF attached for more
 batchSelector.CEXL.pdfpairs0102_0910.pdfpairs1112_1718.pdf 