Message ID: 230
Entry time: Thu Jul 6 09:54:53 2017
|
Author: |
Valérie L |
ExpNbr: |
e748 |
Type: |
RUN |
Category: |
General |
Status: |
Fixed |
Target-Source: |
CD2 |
Subject: |
Run control OK -Runs 339 and 340 |
|
|
After the reboot soft of the AGAVA NUMEXO and realignment of the TGS (time stamp Agava) the situation is stabilized.
The "astreintes" for hardware (Gilles W) and software (Clotilde M) have rebooted from the Terminal the crates (AGAVA).
Antoine Lemasson has reloaded the setup of the GTS.
Charles Houarner and Antoine have checked the configuration for the VME AGAVA
cf the ELOG entry Id=233 indicating the procedure for the correct configuration of Agava before restarting.
[ https://elog.lpc-caen.in2p3.fr/MUST2/233 ]
Now the run control is starting correctly for Numexo.
The correlation plots are checked cf plots below for Chio and Cats.
There were DAQ problems between 7h20 and 9h30. It took ~ 2h to test the restart/init, then after calling the astreintes (at 8h30) it took nearly 1 hour to solve the problem (reboot+ settings of the crates and DAQ. The data runs restarted at 9h32 with run 339.
===========================================================================================
General DAQ e748 /data/e748X/e748/acquisition/run
Run 339 6 JULY start 9h32 STOP 9h43
-r--r--r-- 1 e748 Exxx 65M 6 juil. 09:43 run_0339.dat.06-07-17_09h32m52s
DAQ chio e748 chio /data/e748chioX/e748chio/acquisition/run
-r--r--r-- 1 e748chio Exxx 757K 6 juil. 09:43 run_0339.dat.06-07-17_09h32m40s
===========================================================================================
General DAQ e748
Run 340 6 JULY start 9h47 STOP ...
-rw-r--r-- 1 e748 Exxx 506M 6 juil. 11:07 run_0340.dat.06-07-17_09h47m43s
DAQ chio e748 chio
-rw-r--r-- 1 e748chio Exxx 6,2M 6 juil. 11:12 run_0340.dat.06-07-17_09h47m33s
=========================================================================================== |
|
|
|
|
|
|