Fixede768s Sat Jul 20 23:43:02 2019 mugastRUNGeneralLiFRun 119 (Problem with VXI fixed for the moment)
Run 119.
Or-Vamos= 1430 ---> I=1.43x10^7 pps
Fixede768s Mon Jul 22 08:28:00 2019 mugastOTHERGeneralLiFScalers at start of run124
Fixede768s Mon Jul 22 11:21:25 2019 mugastMUST2Software Pedestals of MG3
Pedestals of MG3_X have changed yesterday, they are back to about 8200 as they should be --> saved in ped_muvi2sec2_22072019_new
We are using wrong pedestals (of about 9600) --> the pedestals are saved under mugast account as ped_muvi2_sec2_22072019_sameas_1807219

We kept the same pedestals but we reduced the pedestal suppression to 0 - 6800 in order not to suppress the data of one other 2 mates.
The attached spectrum shows that all the X of MG3 are recovered (although the impact matrix still does not work)
Fixede768s Tue Jul 23 13:20:20 2019 mugastRUNGeneralN/ABeam stop for canicule
At 13.16 the beam was stopped due to the high temperature.
Bertrand is switching off the magnets of VAMOS.
Fixede768s Wed Jul 24 14:41:09 2019 mugastRUNGeneralN/AVAMOS divison 30
VAMOs division is set to 30
Fixede768s Thu Jul 25 07:00:15 2019 mugastRUNGeneralLiFRun 135 - stop
Qpole 41 lost (Q41). Beam stopped before recovery.
Operator not able to get it back. Will try without waiting on next operator.
Fixede768s Thu Jul 25 12:55:19 2019 mugastAGATAGeneralLiFProblem Crystal 00A during run 140
Problem with crystal 00A at 12h50:
- Very large counting rate 300 k

*Tried a resync as usual but did not work.
* Put in Drain temporarily until issue solved
Fixede768s Thu Jul 25 13:39:42 2019 mugastBEAMGeneralLiFBeam stop due to high temperature
A lot of Qpoles power supplies had to be shutdown.

Beam stopped at 13h30.
Fixede768s Fri Jul 26 14:06:33 2019 mugastONLINEGeneralLiFScreenshots run 151_1
Fixede768s Fri Jul 26 15:47:17 2019 mugastVAMOSHardwareLiFVAMOS division
New VAMOS division : 10.
Fixede768s Fri Jul 26 16:06:18 2019 mugastRUNGeneralLiFRun number 152_1
Fixede768s Fri Jul 26 19:00:15 2019 mugastONLINEGeneral Run number 152_2
Fixede768s Fri Jul 26 23:25:49 2019 mugastONLINEGeneralLiFRun number 152_3
Fixede768s Sat Jul 27 11:02:13 2019 mugastONLINEGeneral figures run 152
Fixede768s Sat Jul 27 16:54:29 2019 mugastAGATAGeneralLiFCurrent full stat on 19Ne
Identified in VAMOS, all the good runs from 112 up to partial 154
Nothing new, a few counts near 2497
Fixede768s Sat Jul 27 21:40:16 2019 mugastRUNGeneralLiFRun 154_5
Fixede768s Tue Jul 30 16:22:21 2019 mugastRUNGeneralLiFBeam is back. Intensity= 7e6 pps. Start a new run : run 160
Run 160.
FixedTEST Wed Feb 12 09:32:17 2020 mugastRUNGeneral3-alphaRun 500 - 3alpha - mugast standalone
RUN 500

start: 11/02/2020 @ 19h00
stop: 12/02/2020 @ 10h00

alpha source test - cooling 14°C

Remarks:
- The two new detectors (MG2 and 6) seem functional;
- MG11 annular, ok for sectors (Y) but many rings have double peaks;
- MM1 current was oscillating yesterday evening with values around 3 uA, this morning it was stable at ~0.55 uA.
FixedTEST Fri Feb 14 17:26:05 2020 mugastOTHERGeneralN/ARun 517 - Pedestal with source
RUN 517

Pedestal run with alpha source
FixedTEST Tue Feb 18 09:20:51 2020 mugastOTHERGeneralN/ABilan Runs de Calibrations
---------
ENERGIE
---------

RUN 500: alpha run, cooling 14°C, (nuit 11 au 12/02/2020)

RUN 501: alpha run, cooling -2°C, (nuit 13 au 14/02/2020)

RUN 517: short alpha run, with pedestals (18/02/2020)


---------
TEMPS
---------

MUVI1 (runs 502-503)
- MG1 : X,Y
- MG3 : X,Y
- MG4 : X,Y
- MG5 : X

MUVI2 (runs 510-511)
- MG7 : X, Y
- MG2 : X
- MG6 :
- MG11 : X

MUVI3 (runs 506-507)
- all OK (X,Y)

MUVI4 (runs 515-516)
- MG9: X, Y

(Rq: Seul MG6 n'a pas de calib T pour le moment, pas de réponse au pulser)