Fixed, e768s, Mon Jul 15 14:29:47 2019, Marlène, MUST2, General, , Masks for MUST2 & Kapton changed for MG5 IMG_20190715_121646_crop_flip.jpgIMG_20190715_122035.jpg
Masks are now correctly mounted

All 4 kaptons from MG5 have been changed
Fixed, e768s, Thu Jul 18 11:52:59 2019, Marlène, OTHER, Hardware, N/A, Division of SQUARE & MUST2 

MUST2 DIV is now 10 (input 7 of GMT)
Fixed, e768s, Sun Jul 21 14:54:28 2019, Marlène, RUN, General, , run 119 scalers run_119_scaler_beam2.pngrun_119_scaler_beam.png
 
Fixed, e768s, Sun Jul 21 16:42:20 2019, Marlène, OFFLINE, General, , Conversion of data from AGATA :update 
When VAMOS VXI crashed (run 118) the Action file was recompiled.
As AGATA conversion is not copying the ACTION file for each run, it used the old version by default (from 16th of july).
Fixed, e768s, Sun Jul 21 17:02:25 2019, Marlène, BEAM, General, , beam intensity in the afternoon run_119_scaler3.png
 
Fixed, e768s, Tue Jul 23 16:19:14 2019, Marlène, OTHER, Hardware, , VAMOS division 
VAMOS division was set 10 instead of 100.
CATS 1 & CATS2 scalers are sent to the two last channels of the scaler
Fixed, TEST, Wed Dec 4 19:19:38 2019, Marlène, GRIT, Hardware, , Modifications of set-up 
We have installed the new MUFEE board in the reaction chamber for MG2. This board is a new version with ATHED.

We have moved the MG9 board to become the board to read the future MUST2 detector at 90 deg. This board is now perpendicular to the other ones. We have
Pending, TEST, Tue Jan 21 17:55:12 2020, Marlène, MUST2, Hardware, , Ovv error on the -5V of CAEN boards BT_referenve_5V_cables_inv_a_comp_referenve_5V_partMUST2BT_referenve_5V_partMUST2_cables_inv_a_comp_referenve_5VBT_referenve_5V_partMUST2BT_referenve_5V
The Ovv error shows on the -5V (first one) of the 3 board (5,3.3,10V for MUST2§squares)
It means that the voltage is over the asked value.
If we ask 5V, we get 5.5V in reality
Fixed, TEST, Wed Jan 22 15:53:25 2020, Marlène, GRIT, Hardware, , Changes for MUGAST2020 
Changes were made for MUGAST 2020 : 
1- the board for MG10 before (2nd square) is now for MG6 new trap
2- the board for MG9 is put vertical and used for the MUST2 at 90 deg
Fixed, TEST, Sun Feb 23 20:50:06 2020, Marlène, GRIT, General, , RUN 115  8x
Screenshots from MUGAST

The impact matrix looks fine but there are sectors missing but in the raw we see 13 sectors (instead of 16)
Fixed, TEST, Mon Feb 24 10:26:29 2020, Marlène, GRIT, General, , infos 
We have changed the range of the TAC FAG-HF to 500ns (it was 200 ns before)

there is no delay on the STOP of MUVI, it is directly the HF clean.
Fixed, e775s, Wed Feb 26 15:02:38 2020, Marlène, RUN, General, , RUN 137 Ex_137.pdfEx_run128_137.pdf
RUN 137
CD2+Au #2
beam intensity 6e+5pps
    Fixed, e775s, Wed Feb 26 15:12:02 2020, Marlène, RUN, General, , RUN 137 8x
Screenshots of RUN137

[quote="Marlène"]RUN 137
    Fixed, e775s, Wed Feb 26 16:19:35 2020, Marlène, RUN, General, , RUN 137 (suite) Ex_Egamma_run137.png
Here is the E gamma versus Excitation energy spectra for run 137

Fixed, , Thu Feb 27 15:56:09 2020, Marlène, RUN, General, , RUN 142 AGATA- 143 VAMOS-MUGAST 
RUN142 on AGATA and  RUN143 on MUGAST/VAMOS

target CD2 (350ug/cm2)
    Fixed, , Thu Feb 27 16:25:45 2020, Marlène, RUN, General, , RUN 142-143 screenshots RUN143_ElabThetaLab.pngRUN143_impact.pngRUN143_tac.pngRUN143_tof.png
[quote="Marlène"]RUN142 on AGATA and  RUN143 on MUGAST/VAMOS

target CD2 (350ug/cm2)
    Fixed, , Thu Feb 27 16:30:53 2020, Marlène, RUN, General, , RUN 142 -143 preliminary analysis  RUN143_ana_Elab_Thetalab.pngRUN143_ana_Ex_Eg.pngRUN143_ana_Ex.png
[quote="Marlène"][quote="Marlène"]RUN142 on AGATA and  RUN143 on MUGAST/VAMOS

target CD2 (350ug/cm2)
Fixed, , Fri Feb 28 11:20:22 2020, Marlène, GRIT, General, , RUN 150 
RUN 150
 target CD2 300 ug/cm2
Beam intensity 4e+5pps
Fixed, e775s, Fri Feb 28 11:21:31 2020, Marlène, RUN, General, , RUN 151 
RUN 151

Change of target now : CD2+AU #2
    Fixed, e775s, Fri Feb 28 14:00:08 2020, Marlène, RUN, General, , RUN 151 beam stop 
[quote="Marlène"]RUN 151

Change of target now : CD2+AU #2