MUGAST, Page 106 of 132
Not logged in
Find
|
Login
Full |
Summary
|
Threaded
|
Show attachments
2636 Entries
Goto page
Previous
1
,
2
,
3
...
105
, 106,
107
...
130
,
131
,
132
Next
Status
ExpNbr
Date
Author
Type
Category
Target-Source
Subject
Fixed
e768s
Wed Jul 24 12:40:49 2019
OttoRun
RUN
General
LiF
Run128
*************************
Run : 128
*************************
Start at 2019-07-24 12:40:32.602728
Test of scalers
Stop at 2019-07-24 12:43:18.414715
Stop comment:
Fixed
Wed Jul 24 12:44:55 2019
UK refugees
OTHER
General
Fire out thanks to de Piffle
Fixed
e768s
Wed Jul 24 13:33:34 2019
OttoRun
RUN
General
LiF
Run129
*************************
Run : 129
*************************
Start at 2019-07-24 13:29:27.436829
Test of scalers
Started with the setting of VAMOS with 15N beam + target. Plate removed.
Stop at 2019-07-24 14:22:17.151753
Stop comment:
type your message here
Fixed
e768s
Wed Jul 24 14:41:09 2019
mugast
RUN
General
N/A
VAMOS divison 30
VAMOs division is set to 30
Fixed
e768s
Wed Jul 24 14:57:51 2019
OttoRun
RUN
General
LiF
Run130
*************************
Run : 130
*************************
Start at 2019-07-24 14:45:43.707908
Test of scalers
Started with the setting of VAMOS with 15N beam + target. Plate removed.
Stop at 2019-07-24 14:57:53.598976
Stop comment:
Fixed
e768s
Wed Jul 24 15:12:07 2019
OttoRun
RUN
General
LiF
Run132
*************************
Run : 132
*************************
Start at 2019-07-24 15:05:21.496150
Test of scalers
Started with the setting of VAMOS with 15N beam + target. Plate removed.
Stop at 2019-07-24 15:53:35.796063
Stop comment:
Fixed
e768s
Wed Jul 24 16:04:04 2019
OttoRun
RUN
General
LiF
Run133
*************************
Run : 133
*************************
Start at 2019-07-24 16:01:41.339572
Stable 15N beam @ ~ 1-2e8 pps
Brho = Tm
target LiF thick number 1
Trigger:
MUGAST
VAMOS %30
BaF2 %100
Stop at 2019-07-24 16:44:55.787916
Stop comment:
type your message here
Fixed
e768s
Wed Jul 24 16:24:18 2019
Nicolas
OTHER
General
19Ne / 19F analog connections
Fixed
e768s
Wed Jul 24 16:51:16 2019
OttoRun
RUN
General
LiF
Run135
*************************
Run : 135
*************************
Start at 2019-07-24 16:43:07.051256
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm (ref Brho = central trajectory)
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 07:21:33.253248
Stop comment:
End of run 135
Fixed
e768s
Wed Jul 24 17:21:27 2019
Diego
OTHER
General
VAMOS Acceptance with different positions of the beam in the target
Fixed
e768s
Wed Jul 24 22:10:04 2019
Chloé, Yorick
ONLINE
General
LiF
Spectra Run 135 24/07/19 22:00
Fixed
e768s
Thu Jul 25 03:58:19 2019
François et Gilbert
RUN
General
LiF
Spectra Run 135 25/07/19 4:00
Second snapshot of run 135
Spectra refreshed
Fixed
e768s
Thu Jul 25 07:00:15 2019
mugast
RUN
General
LiF
Run 135 - stop
Qpole 41 lost (Q41). Beam stopped before recovery.
Operator not able to get it back. Will try without waiting on next operator.
Fixed
e768s
Thu Jul 25 07:23:32 2019
OttoRun
RUN
General
LiF
Run136
*************************
Run : 136
*************************
Start at 2019-07-25 07:23:18.946360
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 07:36:30.334491
Stop comment:
run 136 empty - Geco blocked
Fixed
e768s
Thu Jul 25 08:22:30 2019
OttoRun
RUN
General
LiF
Run137
*************************
Run : 137
*************************
Start at 2019-07-25 08:21:01.510827
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 08:27:20.083016
Stop comment:
stop en astreinte Luc
Fixed
e768s
Thu Jul 25 08:51:36 2019
OttoRun
RUN
General
LiF
Run138
*************************
Run : 138
*************************
Start at 2019-07-25 08:51:28.293968
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 09:38:49.818302
Stop comment:
stop adf file prob
Fixed
e768s
Thu Jul 25 09:47:02 2019
OttoRun
RUN
General
LiF
Run139
*************************
Run : 139
*************************
Start at 2019-07-25 09:46:45.733969
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 11:25:01.666042
Stop comment:
type your message here
Fixed
e768s
Thu Jul 25 11:05:18 2019
Francois de Oliveira
OTHER
General
Previous Papers - alpha-branching ratios for states in the 4-MeV region
In the reaction 15N(7Li,t)19F, the ratio between the measured cross sections is R(3/2+/9/2-)>29. We should get the same ratio in 19Ne. In 19Ne, the 3/2+ state decays with Eg=4033 keV (80%), the second with 2632 keV (100%), gamma efficiency = 4% and 5.5%, this gives a ratio between the number of counts measured in the 2632 keV and in the 4033 keV > 29 x 100/80 x 5.5 / 4 ~ 50.
Fixed
e768s
Thu Jul 25 11:44:00 2019
OttoRun
RUN
General
LiF
Run140
*************************
Run : 140
*************************
Start at 2019-07-25 11:43:45.222331
Stable 15N beam @ ~ 1-2e8 pps
Brho = 0.64 Tm
target LiF thick number 1
Trigger:1100
MUGAST 1500
VAMOS %30 4500
BaF2 %100
DT 20%
Stop at 2019-07-25 13:24:23.295982
Stop comment:
beam stopped due to high temperature
Screenshot attached at the end of the run
Fixed
e768s
Thu Jul 25 12:55:19 2019
mugast
AGATA
General
LiF
Problem Crystal 00A during run 140
Problem with crystal 00A at 12h50:
- Very large counting rate 300 k
*Tried a resync as usual but did not work.
* Put in Drain temporarily until issue solved